Professional Experience:
BAE Systems - Southeast Shipyards Alabama (CONTRACTOR via Sirius Technical) Mobile, AL
Integrated Master Scheduler, Project Controls & Reporting
Integrate individual project schedules to create and maintain integrated master shipyard schedules and capacity plans. Perform weekly audits to
ensure schedule adherence/risk management assessment and to make certain that the logic changes, adjustments to activity/project resources,
duration compression and float management does not undermine the management value of the schedule. Produce, maintain and review weekly
integrated look-ahead schedules, major milestone schedule, resource plans and associated communication tools for each work center working closely
with the shop floor planners and production management that account for work center capacity and identify over-capacity situations that require
additional resources, overtime, and/or subcontractors. Lead the communication of master yard schedules, capacity plans, and associated issues to
program management, engineering, production management, senior company management, and the customer representatives. Work closely with
management to develop, maintain, and improve all project scheduling and integrated scheduling standards, and to assist with training project
schedulers. Serve as the primary back-up for the Scheduling Manager.
03/15 to Present
Mitternight Satsuma, AL
Continuous Process Improvement/Process Engineer
Collaborates with management team in the implementation and coordination of lean initiatives/projects to enhance the organizational effectiveness in
fabrication. Develops and executes new processes or improves existing processes to streamline production work flow and administration support
functions. Work side-by-side with department management and associated work groups to fully implement and assure sustaining mechanisms are in
place. Proactively involves teammates at all levels of the organization to gain their input and support. Works with management to establish and
continuously meet their needs through business/performance metrics. Documents procedures and changes that result from improvement initiatives to
ensure sustaining efforts. Benchmarks industry best practices to identify future improvements and opportunities.
12/14 to 03/15
Project Manager
Responsible for total project administration on one or multiple projects. Overseeing and making decision related to the performance of work related to
sequencing, milestones, delivery, logistics, and customer specification compliance. Coordinated work among assigned trades, support functions,
materials management and subcontractors to promote a synchronized project operation. Support trades in fabrication by coordinating subcontractor
work, material needs & delivery, hold point inspects, on site representatives and customer specification compliance
01/14 to 12/14
Scheduler, Planner, Process Engineer & Production Controls
Developed & implemented detailed, logic driven, resource loaded project scheduling, as well as, the company’s planning structure, allowing the
measurement of work down to a granular level of detail. This level of detail allowed the work scope to be gauged and data to be gathered for both
current work scope inefficiencies and historical information to be used at the estimating phase for future business. Developed & implemented the
reporting system (EVMS reporting) and management tools for gauging the performance of different phases of a job, and the performance of the
supervisors and employees on each job. Established an employee evaluation system/report to ensure accountability as well as compensation for
those performing at or above the standards set. All aspects of the schedule, the plan and the reporting function directly tied into the time charging
system/software for measuring a job on a real time basis. I interacted directly with the company owners, project management, shop floor supervisors,
and customer representatives to make day to day decisions that moved the projects toward completion. I developed and implemented preconstruction
build strategy meeting to assist production in the full understanding of the work scope and customer expectations prior to commencing
the work. When this was first implemented we (management, owners and customers) saw an immediate improvement in work efficiencies.
Implemented a post job deconstruct meeting to document the lessons learned and allow management to understand the hows & whys of the things
that went both right and those things that went wrong, thus allowing the company to estimate, engineer and plan better on similar future projects.
When I started with Mitternight the company had no planning system, no logic driven, resource loaded schedule, no real time shop loading and no
reporting functions to manage the projects.
02/11 to 01/14
Northrop Grumman Ship Systems (CONTRACTOR [10/08 to 10/10] via CDI IT Solutions) Pascagoula, MS
Integrated Master Scheduler/Subject Matter Expert, Project Controls & Reporting
Responsible for the integration of multiple system schedules (106) to display a workable flow process in a master integrated schedule format to
provide the client (DOD) with a well-constructed CPM production schedule (over 97,000 activities/164,000+ relationships). Oversee the development
of the individual system schedules to ensure proper detailed work scope development, system maturity milestone requirements, code structure & work
breakdown structure compliance and logic assignments (using both Gantt and PERT networks extensively) to meet company expectations of an
integrated master production schedule. Create/develop project execution plans and schedules to forecast completion dates and resource
requirements, to identify critical path activities or deliverables and to integrate the deliverables of all resources involved. Maintain project reports on a
daily basis to support management in decision making in both execution and recovery scenarios. Resolved problems and assesses progress against
established schedule/plan baseline.
10/08 to 02/11
Parsons Construction Management (CONTRACTOR via Sirius Technical) Mobile, AL
Gulf Coast Region/ThyssenKrupp Steel USA – Lead Scheduler/Project Controls Specialist (EVMS)
Oversee the development of the contractor schedule to ensure proper detailed work scope development, logic assignments and man power utilization
to meet company/industry standards and sound scheduling practices. Monitor, analyze, and forecast the project's status using earned value
methodology. Identify and anticipate schedule deviations and/or trends.. Responsible for the integration of multiple contractors’ schedules to display a
workable process in an integrated master schedule format to provide the client with a well-constructed CPM production schedule.
04/08 to 10/08
Page1
John “David” Lancaster
Professional Experience Continued
Noble Drilling Services (CONTRACTOR via Ideal Marine) Houston, TX/Pascagoula, MS
Gulf of Mexico – Regional Lead Scheduler
Responsible for ensuring the contractor provides and maintains a well-constructed production schedule. Accountable for producing production reports,
earned value management and schedules for company representatives to perform weekly work assignments based on the current scheduled work, as
well as, recovery schedules or corrective active plans (managing risk assessment) for immediate action on projects that have become behind the
baseline scheduled dates. My oil drilling experience includes new construction, maintenance and upgrades on semi-submersibles and jackup oil rigs.
10/06 to 04/08
Chevron Texaco (CONTRACTOR via Sirius Technical) Pascagoula, MS
04/05 to 10/06
Routine Reliability & Capital Improvement Scheduler
Responsible for maintaining the routine reliability/maintenance system for transfer, storage & shipping areas of the refinery. Accountable for providing
refinery maintenance crews with planned, preventive & corrective maintenance work. Provide weekly plans for maintenance crews, construction crews
and all supporting contractors, on site material and equipment to ensure a flawless execution of the work. Team player in the evolution of the routine
reliability/capital improvement work process system, through the use of schedule attainment, manpower forecast and leveling of resources to ensure a
constant work load and execution the of planned work.
Bender Shipbuilding & Repair, Inc. Mobile, AL
Repair Yard Master Scheduler (Interim Planning Manager, Feb to May 2001)
Responsible for the development, creation, and full utilization of project schedules for all ship repair jobs (as many as 19 projects within 6 months).
Gathered, reviewed, and analyzed the specifications to ensure all requirements are met. Allocate budget/cost from the assigned estimate and balanced
resources (man power, material, subcontractors & equipment) to achieve a schedule that meets or exceeds the contract time frame. Assisted estimating -
when overloaded or a complex schedule is required - in development of schedules for bidding on prospective jobs. Developed and taught “in house”
Primavera training classes for beginners, intermediates, and advanced. Project scheduler from numerous commercial, Navy/NAVSEA, USNS, & MSC
repair jobs.
02/99 to 02/05
Alabama Shipyard, Inc. Mobile, AL
Lead Project Scheduler / Primavera Network Administrator
Responsible for creating and utilizing a master project schedule which has allowed the Production Planning Department to efficiently project job
completion dates, manpower requirements, and schedule delays. Development and introduction of a much needed Productivity Reporting System.
07/97 to 10/98
HAMM Marine, Inc. Pascagoula, MS
Sole Project Scheduler
Responsible for the creation and full utilization of master project schedule that has allowed the company to efficiently project manpower requirements, by
craft and job, and implemented the use of Resource Leveling to maintain a steady work load for each craft “yard wide.”
08/96 to 07/97
Litton/Ingalls Shipbuilding, Pascagoula, MS
Production Planner
Develop Integrated Schedule Progress Indicators (ISPI's) for off-site US Navy Aegis Cruiser Life Cycle Management Program (LCMP).
Test and Trials Operator
Accountable for all Main Propulsion Engineering Systems and Ship Service Generator system operations, testing and trials.
United States Navy, USS Gallery (FFG-26)
Educational Background:
Mississippi Gulf Coast Community College, Jackson County Campus
Software Utilization:
I have comprehensive knowledge, experience and proficiency with Primavera (P6) 8.4, Microsoft Office Suite, Microsoft Project 2010 and Earned
Value Management System/performance measurement techniques
Personal:
· Noted for professional performance, initiative and attention to detail.
· Able to be multi-tasked and complete the assigned jobs above management’s expectations.
· Noted as the “go to guy” to accomplish major task within & outside of my job boundary.
· Developed spreadsheets, charts and graphs to accommodate both in house management, production personnel and the customers representatives.
Gas Turbine Systems Technician Mechanic, Work Center Supervisor
Supervised/performed all preventive and corrective maintenance on main propulsion equipment. Responsible for all aspects of main propulsion.
07/87 to 07/91
07/91 to 08/96
Page2